photo Rudi Hermawan - Beritajakarta.id

Process of Tegal Alur Retention Basin Construction Reaches 70 Percent

Tegal Alur Retention Basin construction in Kalideres, West Jakarta has reached 70 percent.

This retention basin is made to overcome inundation in Lokbin Tegal Alur due to local rain and tidal flood

West Jakarta Water Resources (SDA) Sub-agency's Flood Control Maintenance System for Clean Water and Wastewater Section Head, Wawan conveyed, this retention basin is as wide as 2,410 square meters and depth of 3 meters on 3,640 square meters land.

"This retention basin is made to overcome inundation in Lokbin Tegal Alur due to local rain and tidal flood," he said, Tuesday (11/10).

Retention Basin Construction in Tegal Alur is Expected to Overcome Inundation

According to him, this retention walls can accommodate up to 7,230 cubic meters water to prepare for water runoff from Semongol River or tidal flood.

"We have started the construction since September and targeted it to finish in December," he closed.

Linked News
Popular News indeks
  1. Monas Prepares to Greet Visitors This Eid Holiday

    access_time30-03-2025 remove_red_eye687 personDessy Suciati
  2. Jakarta Vice Governor Rano Wishes a Happy Eid al-Fitr 1446 Hijri

    access_time31-03-2025 remove_red_eye600 personFolmer
  3. Foul Smell Around JGC Clarified Not Coming from Rorotan RDF

    access_time28-03-2025 remove_red_eye437 personAldi Geri Lumban Tobing
  4. Odd-Even Policy in Jakarta Put on Hold for Eid Break

    access_time28-03-2025 remove_red_eye322 personAldi Geri Lumban Tobing
  5. 49,101 Local and Foreign Tourists Swarm Monas

    access_time02-04-2025 remove_red_eye274 personBudhi Firmansyah Surapati

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik